A manufacturing line has three sequential stages: Stage 1 (6 min/unit), Stage 2 (8 min/unit), and Stage 3 (5 min/unit). If the market demand is 10 units per hour, what is the actual Flow Rate of the system?
A
10 units/hr
B
7.5 units/hr
C
8.5 units/hr
D
12 units/hr