Module 04: Capital Budgeting
Module 4
Module Overview
Capital budgeting is the process a firm undertakes to evaluate potential investment projects: which of the projects on its table should be accepted and which rejected. Module 4 has two halves. The first half compares four decision techniques: net present value (NPV), the payback period, the discounted payback period and the internal rate of return (IRR), with the strengths and weaknesses of each, and a long look at where IRR goes wrong (no IRR, multiple IRRs, lending versus borrowing, and ranking mutually exclusive projects that differ in scale or life). The verdict is that NPV is the most superior technique, and that IRR can be rescued for mutually exclusive projects only by computing it on incremental cash flows. The second half answers the question the first half takes for granted: where do the project cash flows come from? Five rules govern estimating project cash flows: use cash flow, not accounting income; work on an incremental basis; treat inflation consistently; separate investment from financing; and forecast after taxes. The module ends with a complete project appraisal that builds an income statement, operating cash flow, working capital flows and an after-tax salvage value into a single NPV.
Memory hook: Every technique is judged against one goal: the financial goal of the corporation is to maximise shareholder wealth. Accept projects that increase it, reject projects that decrease it. NPV measures that change directly, which is why it wins.
4.1 Introduction to Capital Budgeting
4.1.1 What Makes an Investment Rule Bad
An investment rule leads to inferior decisions if it does any of the following:
| A bad rule... | Why that is a flaw |
|---|---|
| Ignores the time value of money | Time has money value, so a rupee later is worth less than a rupee today |
| Is affected by the tastes and preferences of managers | Managers' preferences have nothing to do with whether a project adds value |
| Is influenced by the choice of accounting method | The accounting method predominantly does not affect cash flows, so it should not affect the accept or reject decision |
| Depends on the profitability of the company's existing business | Existing profitability has nothing to do with whether this project adds value |
Use these four tests to grade every technique in the module.
4.1.2 What CFOs Actually Use
A survey of chief financial officers of US companies (Graham and Harvey, "The Theory and Practice of Finance: Evidence from the Field", Journal of Financial Economics, 2001) asked which techniques they use to evaluate investment projects:
| Technique | Share of CFOs using it |
|---|---|
| Internal rate of return (IRR) | 76% |
| Net present value (NPV) | 75% |
| Payback period | 57% |
| Book rate of return | 20% |
Because the book rate of return is the least used, the course does not cover it. The percentages add up to more than 100% because a manager can use more than one technique to evaluate the same project.
4.2 Net Present Value
NPV depends solely on two things: the forecasted cash flows from the project and the opportunity cost of capital for the project. NPV:
- uses cash flows (not accounting profits),
- uses all the cash flows of the project, and
- discounts them properly, that is, at a rate that reflects their risk.
A project with a positive NPV increases shareholder wealth; one with a negative NPV decreases it. NPV is therefore consistent with the goal of shareholder wealth maximisation.
Acceptance criterion: accept projects with NPV > 0; reject projects with NPV < 0.
The adding-up property. Because NPVs are all measured in today's rupees, they can be added:
| NPV: advantages | NPV: disadvantage |
|---|---|
| Recognises the time value of money | Not as easy to communicate to a layperson as other techniques. Telling someone "the NPV is Rs 100" does not tell them whether that is good enough |
| Provides a clear benchmark for acceptance (zero), which does not depend on managers' tastes and preferences | |
| Not affected by the company's choice of accounting method, because it uses cash flows |
4.3 Payback Period
The payback period is the time a project takes to "pay back", or recover, its initial investment: the number of years before the cumulative cash flow equals the initial outlay.
Acceptance criterion: accept projects whose payback period is less than or equal to a specified cutoff period, set by management.
| Payback: advantages | Payback: disadvantages |
|---|---|
| Easy to understand and calculate | No clear benchmark: the cutoff is arbitrary and depends on managers' tastes and preferences |
| Biased towards liquidity: favours projects that pay back quickly | Biased against long-term projects: ignores all cash flows after the cutoff date |
| Ignores the time value of money: gives equal weight to all cash flows before the cutoff |
Worked example: payback versus NPV for projects A, B and C. Each project costs USD 2,000 today and the opportunity cost of capital is 10%. The management cutoff is 2 years.
| Project | Payback period | NPV at 10% | ||||
|---|---|---|---|---|---|---|
| A | −2,000 | 500 | 500 | 5,000 | 3 years (reject) | +2,624 (accept) |
| B | −2,000 | 500 | 1,800 | 0 | 2 years (accept) | −58 (reject) |
| C | −2,000 | 1,800 | 500 | 0 | 2 years (accept) | +50 (accept) |
The NPV of project A, for example:
Answer: payback accepts B and C and rejects A; NPV accepts A and C and rejects B. Payback makes two mistakes: it rejects A, which should be accepted, and accepts B, which should be rejected.
The example exposes both weaknesses:
- It ignores all cash flows after the cutoff. Project A's USD 5,000 in year 3 is simply ignored.
- It gives equal weight to cash flows before the cutoff. Payback cannot tell apart B (500 then 1,800) and C (1,800 then 500), although C, which receives the big cash flow sooner, is worth more.
4.4 Discounted Payback Period
The discounted payback period is the time a project takes to pay back its initial investment on a discounted basis, that is, after taking the time value of money into account.
Acceptance criterion: accept projects whose discounted payback period is less than or equal to a specified cutoff, again set by management.
| Discounted payback: advantages | Discounted payback: disadvantages |
|---|---|
| Will never accept a negative NPV project | No clear benchmark: the cutoff is arbitrary |
| Biased towards liquidity | Biased against long-term projects: ignores all cash flows after the cutoff |
| Takes the time value of money into account |
Worked example: discounted payback for projects A, B and C. Same projects, 10% opportunity cost, 2-year cutoff. First discount every cash flow: for example, the PV of A's year 1 cash flow is 500 ÷ 1.1 = 455, of its year 2 cash flow 500 ÷ 1.1² = 413, and of its year 3 cash flow 5,000 ÷ 1.1³ = 3,757.
| Project | PV of | PV of | PV of | PV of | Discounted payback | NPV at 10% |
|---|---|---|---|---|---|---|
| A | −2,000 | 455 | 413 | 3,757 | 3 years (reject) | +2,624 (accept) |
| B | −2,000 | 455 | 1,488 | 0 | Not defined (reject) | −58 (reject) |
| C | −2,000 | 1,636 | 413 | 0 | 2 years (accept) | +50 (accept) |
Project A recovers 455 by year 1 and 455 + 413 = 868 by year 2, and passes 2,000 only in year 3. Project B recovers 455 + 1,488 = 1,943 by year 2 and nothing after, so it never recovers its 2,000 in discounted terms. Project C recovers 1,636 + 413 = 2,049 by year 2.
Answer: discounted payback accepts only C. Its only mistake is rejecting A, because it ignores A's discounted year 3 cash flow of 3,757. It correctly rejects B.
Why discounted payback never accepts a negative NPV project. If a project's NPV is negative, the present value of all its inflows is less than its outlay, so the investment is never recovered in discounted terms. The discounted payback period is then not defined, and the project cannot pass any cutoff.
Common trap: Discounted payback fixes the time-value flaw of simple payback, but not the cutoff flaw. Both methods still ignore everything after the cutoff, which is why both reject the excellent project A.
4.5 Internal Rate of Return
4.5.1 Definition and the IRR Rule
The internal rate of return (IRR) is the discount rate that makes NPV equal to zero.
Worked example: a one-year investment. You invest Rs 100 today and receive Rs 150 after a year. Mentally, the profit is 50 on an investment of 100, a return of 50%. As a project:
Setting NPV to zero turns into the IRR:
Answer: IRR = 50%, the same as the mental calculation. For a single period the return is easy to see; for a multi-year project it is not, and that is what the IRR is for.
Acceptance criterion: accept projects for which IRR > opportunity cost of capital (just as you accept an investment whose rate of return exceeds what you could earn elsewhere at the same risk).
| IRR: advantages | IRR: disadvantages |
|---|---|
| Considers the time value of money | Does not distinguish between investing and borrowing decisions |
| Provides a clear benchmark (the opportunity cost of capital), independent of managers' preferences | IRR may not exist |
| Easy to understand and communicate: a layperson understands "we accept projects that earn at least 20%" | There may be multiple IRRs |
| Problems with mutually exclusive projects that differ in scale of investment or economic life |
4.5.2 Computing IRR: The Turbo-Powered Machine Tool Gadget
You can buy a turbo-powered machine tool gadget for USD 4,000. It generates USD 2,000 at the end of year 1 and USD 4,000 at the end of year 2.
This is a quadratic equation. Only real, positive values of IRR are of interest, and there is just one.
Answer: IRR = 28.08%. Accept the gadget as long as the opportunity cost of capital is below 28.08%.
Why "internal"? Computing the IRR needs only the magnitude and timing of the project's own cash flows: nothing external to the project. In particular, computing IRR does not need the opportunity cost of capital. You need the opportunity cost only to decide, by comparing it with the IRR.
4.5.3 Computing IRR in Excel
Excel's IRR function needs only one required argument, the array of cash flows, and accepts an optional guess.
- Enter the years in one row (Year 0, Year 1, Year 2) and the cash flows beneath them: −4,000, 2,000, 4,000.
- In an empty cell, type the
IRRfunction and select the range holding the cash flows (including the year 0 outflow). - Press Enter. Excel returns 28.08%.
=IRR(B2:D2)
=IRR(B2:D2, 0.10)
The second argument is the guess, which defaults to 10%. Excel returns the IRR closest to the guess. When a project has multiple IRRs, keep varying the guess to make Excel reveal each one.
4.5.4 The NPV Profile: When NPV and IRR Agree
Plot NPV (y-axis) against the discount rate (x-axis) for the gadget. The curve slopes downward and crosses the x-axis at 28.08%, the IRR.
| Region of the NPV profile | NPV | IRR rule says | NPV rule says |
|---|---|---|---|
| Opportunity cost below IRR | Positive | Accept | Accept |
| Opportunity cost equal to IRR | Zero | Indifferent | Indifferent |
| Opportunity cost above IRR | Negative | Reject | Reject |
Formula: NPV and IRR give the same accept or reject decision as long as the project's NPV is a continuously declining function of the discount rate. If NPV increases with the discount rate, the two rules disagree.
4.5.5 IRR Is Not the Opportunity Cost of Capital
| IRR | Opportunity cost of capital | |
|---|---|---|
| What it is | A profitability measure | The expected return investors can achieve in financial markets at the same level of risk |
| Depends on | Solely the amount and timing of the project's cash flows | The risk of the proposed project (higher risk, higher opportunity cost) |
| Role in the decision | The project's return | The hurdle the return must beat |
4.6 Pitfalls of IRR
4.6.1 Pitfall 1: The IRR May Not Exist
| Project | IRR | NPV at 10% | |||
|---|---|---|---|---|---|
| F | −1,000 | +3,000 | −2,500 | None | −339 |
Project F has a negative NPV at every discount rate: its NPV profile never cuts the discount-rate axis, so no rate makes NPV zero. A project could equally have a positive NPV at every rate, and it too would have no IRR. With no IRR there is nothing to compare with the opportunity cost of capital, and the IRR rule cannot decide.
4.6.2 Pitfall 2: Multiple IRRs
Project G costs USD 30 billion, produces USD 10 billion at the end of each year for 9 years, and incurs USD 65 billion of cleanup costs at the end of year 10.
| Year | 0 | 1 to 9 | 10 |
|---|---|---|---|
| Cash flow (USD billion) | −30 | +10 each year | −65 |
The NPV equation is a polynomial of degree 10, which could have up to 10 roots, but only positive real roots matter for IRR. Descartes' rule of signs says there can be as many positive real roots as there are changes of sign in the cash flows. G has two sign changes (−30 to +10 between years 0 and 1, and +10 to −65 between years 9 and 10), so it can have up to two IRRs. This is a necessary, not a sufficient, condition for two roots.
Here both exist: NPV is zero at 3.5% and at 19.54%. Which IRR should be compared with the opportunity cost of capital? There is no answer from the IRR rule. The NPV profile shows NPV is positive between the two, so take up the project if the opportunity cost of capital is between 3.5% and 19.54%.
4.6.3 Pitfall 3: Investing (Lending) Versus Borrowing
| Project | IRR | NPV at 10% | ||
|---|---|---|---|---|
| D (investing or lending) | −1,000 | +1,500 | 50% | +364 |
| E (borrowing) | +1,000 | −1,500 | 50% | −364 |
Both projects have the same 10% opportunity cost and the same 50% IRR, yet D has a positive NPV and E a negative one. The IRR method cannot distinguish between investing and borrowing.
| Investing or lending | Borrowing | |
|---|---|---|
| Cash flow pattern | − + + + (outflow today, inflows later) | + − − − (inflow today, outflows later) |
| What you want | As high a return as possible | The lender to earn as low a return as possible |
| NPV as the discount rate rises | Decreases | Increases |
| Correct IRR rule | Accept if IRR > opportunity cost | Accept if IRR < opportunity cost |
Project E is a borrowing: its IRR (50%) exceeds the 10% opportunity cost, so under the modified rule it is rejected, which agrees with its negative NPV.
A real borrowing-type project: selling insurance. An insurance company receives premiums up front (inflow today) and pays claims later (outflows in the future). Its policies have a borrowing pattern, so the IRR rule must be reversed: accept if IRR is below the opportunity cost of capital.
4.6.4 Independent, Dependent and Mutually Exclusive Projects
| Type | Definition | Example | Decision |
|---|---|---|---|
| Independent | Acceptance or rejection does not prevent acceptance of other projects | A or B or both | Accept all projects that meet the acceptance criterion |
| Dependent (contingent) | Acceptance depends on acceptance of one or more other projects | A can be accepted only if B is | Evaluate together |
| Mutually exclusive | Acceptance prevents acceptance of one or more alternatives | Either A or B, but not both | Rank all projects and select the best |
IRR is unreliable for ranking mutually exclusive projects, in two situations.
4.6.5 Pitfall 4A: Mutually Exclusive Projects That Differ in Scale
| Project | IRR | NPV at 10% | ||
|---|---|---|---|---|
| H | −10,000 | +20,000 | 100% | +8,182 |
| I | −20,000 | +35,000 | 75% | +11,818 |
| I − H | −10,000 | +15,000 | 50% | +3,636 |
H has the higher IRR, but I has the higher NPV. NPV measures the change in shareholder wealth from accepting a project, and the goal is to maximise that wealth, so choose I. IRR misleads because I has a bigger scale of investment: a lower percentage return on a larger investment can add more wealth.
The fix: IRR on incremental cash flows. Compute the cash flows of the extra investment, I minus H: −10,000 today and +15,000 in a year. Its IRR is 50%, well above the 10% opportunity cost, so I is incrementally superior to H: the extra USD 10,000 earns more than it costs.
Which way round? Subtract so that the first incremental cash flow is negative, making the incremental project look like a traditional investment (an outflow followed by inflows). Here that means I − H, not H − I.
4.6.6 Pitfall 4B: Mutually Exclusive Projects That Differ in Economic Life
Project J lasts 3 years; project K is perpetual. Both cost USD 9,000 (the same scale) and have a 10% opportunity cost.
| Project | onwards | IRR | NPV at 10% | |||||
|---|---|---|---|---|---|---|---|---|
| J | −9,000 | +6,000 | +5,000 | +4,000 | 0 | 0 | 33% | +3,592 |
| K | −9,000 | +1,800 | +1,800 | +1,800 | +1,800 | +1,800 forever | 20% | +9,000 |
| K − J | 0 | −4,200 | −3,200 | −2,200 | +1,800 | +1,800 forever | 15.6% | +5,408 |
K's NPV is 1,800 ÷ 0.10 − 9,000 = 9,000. J has the higher IRR, but K has the higher NPV. IRR is unreliable when projects have different economic lives (or different patterns of cash flows over time).
The NPV profiles of J and K cross at 15.6%:
| Opportunity cost of capital | Better project |
|---|---|
| Below 15.6% | K has the higher NPV |
| Exactly 15.6% | Both have the same NPV |
| Above 15.6% | J has the higher NPV |
At 10%, K is superior. The incremental project K − J (first cash flow negative, at year 1) has an IRR of 15.6% (found with Excel, not by hand), well above 10%, so K is incrementally superior to J. The incremental IRR is exactly the crossover rate of the two NPV profiles.
Memory hook: The incremental IRR is the discount rate at which you are indifferent between the two projects. If your opportunity cost is below it, take the bigger or longer project.
4.6.7 Limits of the Incremental Trick, and Why IRR Survives
- The incremental cash flow trick works only if the two projects have the same risk, and hence the same opportunity cost of capital.
- The incremental cash flows can themselves have multiple IRRs or no IRR. The trick is not foolproof.
- So, given a choice, always prefer NPV.
Why is IRR as popular as NPV despite its flaws? Because computing IRR does not need the opportunity cost of capital, only the magnitude and timing of the cash flows. Managers often do not know a project's exact opportunity cost; they can still compute the IRR, but not a precise NPV.
4.6.8 The Four Techniques Compared
| Criterion | NPV | Payback | Discounted payback | IRR |
|---|---|---|---|---|
| Time value of money | Yes | No | Yes | Yes |
| Uses all cash flows | Yes | No (ignores those after cutoff) | No (ignores those after cutoff) | Yes |
| Clear benchmark | Yes (zero) | No (arbitrary cutoff) | No (arbitrary cutoff) | Yes (opportunity cost) |
| Ever accepts a negative NPV project? | No | Yes | No | Possible if misapplied (borrowing, multiple IRRs) |
| Adding-up property | Yes, the only one | No | No | No |
| Easy to communicate | Least | Easy | Easy | Easy |
| Reliable for mutually exclusive projects | Yes | No | No | No (scale, life) unless incremental |
4.7 Capital Budgeting Practice Problems
4.7.1 Problem 1: NPV, Payback and Discounted Payback
Opportunity cost of capital 10%, cutoff 3 years.
| Project | ||||||
|---|---|---|---|---|---|---|
| A | −1,000 | 1,000 | 0 | 0 | 0 | 0 |
| B | −2,000 | 1,000 | 1,000 | 4,000 | 1,000 | 1,000 |
| C | −3,000 | 1,000 | 1,000 | 0 | 1,000 | 1,000 |
Answer: A −91, B +4,045, C +39. B and C have positive NPVs.
(b) Payback. A recovers 1,000 in year 1 (1 year); B recovers 2,000 by year 2 (2 years); C reaches 3,000 only in year 4 because year 3 brings nothing (4 years).
(c) Payback rule with a 3-year cutoff: accept A and B, reject C. (Payback accepts A, a negative NPV project, and rejects C, a positive NPV project.)
(d) Discounted payback. Discount each cash flow at 10%:
| Project | PV | PV | PV | PV | PV | PV | NPV | Discounted payback |
|---|---|---|---|---|---|---|---|---|
| A | −1,000 | 909 | 0 | 0 | 0 | 0 | −91 | Not defined |
| B | −2,000 | 909 | 826 | 3,005 | 683 | 621 | +4,045 | 3 years |
| C | −3,000 | 909 | 826 | 0 | 683 | 621 | +39 | 5 years |
A never recovers its 1,000 in discounted terms. B has recovered 909 + 826 = 1,735 by year 2 and passes 2,000 in year 3. C needs all five years (909 + 826 + 683 + 621 = 3,039).
(e) Discounted payback rule with a 3-year cutoff: accept only B (its discounted payback equals the cutoff). A can never be accepted whatever the cutoff, because it has a negative NPV.
4.7.2 Problem 2: Mr. Simply Simple and the Incremental IRR
Mr. Simply Simple, president of Simple Enterprises, must choose between two investments (USD thousands). The opportunity cost of capital is 9%. He is tempted by B, which has the higher IRR.
| Project | IRR | NPV at 9% | |||
|---|---|---|---|---|---|
| A | −400 | 250 | 300 | 23% | 81.86 |
| B | −200 | 140 | 179 | 36% | 79.10 |
| A − B | −200 | 110 | 121 | 10% | 2.76 |
(a) Why choosing the higher IRR is wrong. The projects are mutually exclusive (he must choose one) and differ in scale (A needs twice the investment). IRR is unreliable for ranking such projects: A can have a lower IRR and a higher NPV.
(b) Adapting the IRR rule. Compute A − B (so the first cash flow is negative) and find its IRR.
Multiply through by and let :
Solve with the quadratic formula, where , , . The discriminant must be non-negative for real roots:
Only the positive real root matters: , so .
Answer: the incremental IRR is 10%, above the 9% opportunity cost, so A is incrementally superior to B. Choose A.
Answer: A's NPV (USD 81.86 thousand) exceeds B's (USD 79.10 thousand) by 2.76, the NPV of A − B. NPV and incremental IRR agree.
4.8 Estimating Project Cash Flows, Rule 1: Cash Flow Is Not Accounting Income
So far the cash flows were given. In real life they must be estimated, and five rules govern how.
| Rule | Statement |
|---|---|
| Rule 1 | Do not confuse cash flow with accounting income or net profit |
| Rule 2 | Estimate cash flows on an incremental basis |
| Rule 3 | Treat inflation consistently |
| Rule 4 | Separate investment and financing decisions |
| Rule 5 | Forecast cash flows after taxes |
4.8.1 Cash Flow Versus Accounting Income
Accounting income (net profit, profit after tax or PAT) may be more or less than the project's cash flow in a given period. The purpose of accounting income is to show how well a firm is performing. What capital budgeting needs is the project-related cash flow, also called net cash flow (NCF) or free cash flow (FCF) (the two terms mean the same): the net cash generated or required by a specific investment project in a given year after paying for operating costs, taxes and necessary capital expenditures.
4.8.2 Operating Cash Flow: Three Equivalent Approaches
The derivation: taxes are . Substituting into the top-down form:
Exam tip: All three approaches give the same OCF. Use whichever matches the data you are given. The full appraisal in 4.13 uses the bottom-up approach.
4.8.3 Working Capital
Working capital is the capital needed for the day-to-day operations of the project (or firm). Its three main components are inventory, accounts receivable (AR) and accounts payable (AP).
The cash cycle. A firm buys raw materials from suppliers, on credit, and pays them some time later: cash goes out of the business. The raw materials become finished goods, which are sold to customers, on credit, and the customers pay some time after the sale: cash comes back. The period from when cash goes out to when it comes back is the cash cycle, and net working capital measures the amount of cash tied up in operations during it.
| Working capital event | Cash flow |
|---|---|
| Initial investment in working capital (most projects need one) | Outflow |
| Increase during the project (rising sales usually need more working capital) | Outflow |
| Recovery at the end of the project (inventories sold, AR collected) | Inflow |
Worked example: working capital for a four-year project (Rs). The project starts in 2026 and ends in 2030.
| 2026 | 2027 | 2028 | 2029 | 2030 | |
|---|---|---|---|---|---|
| Accounts receivable | 0 | 1,50,000 | 2,25,000 | 1,90,000 | 0 |
| Inventory | 75,000 | 1,30,000 | 1,30,000 | 95,000 | 0 |
| Accounts payable | 25,000 | 50,000 | 50,000 | 35,000 | 0 |
For 2026 (NWC in 2025 was zero, since all three components were zero):
| 2026 | 2027 | 2028 | 2029 | 2030 | |
|---|---|---|---|---|---|
| Net working capital | 50,000 | 2,30,000 | 3,05,000 | 2,50,000 | 0 |
| Change in NWC | 50,000 | 1,80,000 | 75,000 | −55,000 | −2,50,000 |
| Cash flow from changes in NWC | −50,000 | −1,80,000 | −75,000 | +55,000 | +2,50,000 |
Answer: the project ties up cash in 2026 to 2028 and releases it in 2029 and 2030; the total outflows (3,05,000) exactly equal the total inflows, because all working capital is recovered by the end.
4.9 Rule 2: Estimate Cash Flows on an Incremental Basis
The value of a project depends on all the additional (incremental) cash flows that follow from accepting it. The sub-rules:
1. Include all incidental effects (the project's effects on the firm's existing business).
| Effect | Meaning | Example | Cash flow |
|---|---|---|---|
| Negative incidental effect | The new project cannibalises sales of the existing business | A maker of internal combustion engine two-wheelers starts an electric vehicle project; sales of its existing two-wheelers may fall | Outflow |
| Positive incidental effect | The new project helps the existing business grow | Inflow |
2. Forecast product sales, but also recognise after-sales cash flows. A new electric vehicle plant should count not only vehicle sales but also revenue from services and spare parts that come later (inflow).
3. Remember salvage value. At the end of its useful life, equipment may have a residual value when disposed of. Salvage value net of any taxes is a cash inflow.
4. Include the opportunity cost of using an existing resource. The cost of a resource may be relevant even when no cash changes hands. A resource the firm already owns is not free: its opportunity cost is the cash it could generate if the project were rejected and the resource were sold or put to another productive use (an incremental outflow).
| Project life | Opportunity cost of an existing resource |
|---|---|
| Perpetual project | The resource's market price. Land that could be sold for Rs 50 lakh has an opportunity cost of Rs 50 lakh |
| Finite-life project | The market rent of the resource over the life of the project |
5. Beware of allocated overhead costs. Overheads are expenses incurred to support the company's business (the CEO's salary is the classic example). They may not be tied to any project, but they must be paid for, so accountants allocate a charge for them to each project. Include only the extra overhead expenses that the project would actually cause. Merely allocating existing overheads is not a project cash flow.
6. Forget sunk costs. Sunk costs are past, irreversible outflows. Accepting or rejecting the project cannot change them, so they are ignored (no cash flow).
Memory hook: Ask one question of every item: "Does this cash flow happen if and only if we take the project?" If yes, include it. If it happens either way (sunk costs, existing overheads), ignore it.
4.10 Rules 3, 4 and 5
Rule 3: Treat inflation consistently. Discount nominal cash flows at nominal rates and real cash flows at real rates; both give the same NPV. Never discount real cash flows at nominal rates or nominal cash flows at real rates. Since market interest rates are usually quoted in nominal terms, you will usually work with nominal cash flows and a nominal rate.
Rule 4: Separate investment and financing decisions. Standard practice is to forecast cash flows assuming the project is all-equity financed, ignoring financing side effects. Any extra value from financing decisions is considered separately. The reason: you want to know whether the project in itself, as an investment decision, adds value. So if a firm finances a project by issuing debt, you ignore the debt proceeds and the interest and principal repayments when estimating project cash flows.
Rule 5: Forecast cash flows after taxes. Taxes are an expense just like wages and raw materials, so cash flows must be estimated on an after-tax basis.
4.11 Practice: Identifying Incremental Cash Flows
4.11.1 Problem 3: Classify Each Activity
| Project-related activity | Classification | Reason |
|---|---|---|
| Capital expenditure (investment) | Incremental outflow | Cash spent on the project |
| Disposal of plant and machinery with salvage value | Incremental inflow | Residual value realised at the end |
| Initial investment in working capital | Incremental outflow | Cash tied up in operations |
| Increase in working capital from one year to the next | Incremental outflow | Additional cash must be invested |
| No change in working capital from one year to the next | No cash flow | Nothing is invested or released |
| Decrease in working capital from one year to the next | Incremental inflow | Working capital is released |
| Recovery of working capital at the end of the project | Incremental inflow | Inventories sold, receivables collected |
| Opportunity cost of using an existing resource | Incremental outflow | The resource can no longer be put to its other use |
| Sunk cost | No cash flow | Irrecoverable whatever you decide |
| Positive incidental effect | Incremental inflow | Helps the existing business |
| Negative incidental effect | Incremental outflow | Hurts the existing business |
| Allocation of existing overhead costs | No cash flow | No additional overhead results from the project |
| Savings in the firm's taxes due to losses on the project | Incremental inflow | Project losses reduce taxable profit elsewhere in the firm |
| Proceeds from borrowing to finance capital expenditure | Ignore | A financing decision (Rule 4) |
| Periodic interest payments on that loan | Ignore | A financing decision (Rule 4) |
4.11.2 Problem 4: A New Manufacturing Plant
The firm is deciding whether to build a new manufacturing plant. The site is already owned, but existing buildings would have to be demolished. Which items are incremental cash flows?
| Item | Incremental? | Reason |
|---|---|---|
| (a) Market value of the site and existing buildings | Yes (outflow) | Opportunity cost of an existing resource |
| (b) Demolition costs and site clearance | Yes (outflow) | Incurred only because of the project |
| (c) Cost of a new access road put in last year | No | Sunk cost |
| (d) Lost earnings on other products due to executive time spent on the new facility | Yes (outflow) | Negative incidental effect |
| (e) A proportion of the cost of leasing the president's jet airplane | No | Allocation of existing overhead |
| (f) Future depreciation of the new plant | No | Depreciation is an allocation of cost, not a cash expense |
| (g) Reduction in the corporation's tax bill from tax depreciation of the new plant | Yes (inflow) | The depreciation tax shield is real cash saved |
| (h) Initial investment in inventories of raw materials | Yes (outflow) | Working capital investment |
| (i) Money already spent on the engineering design of the new plant | No | Sunk cost |
Common trap: Items (f) and (g) look like the same thing. They are not. Depreciation itself is not a cash flow; the tax saved because of depreciation is a cash flow.
4.12 Inflation and Project NPV (Problem 5)
A project costs Rs 100 today and produces real cash flows of Rs 35, Rs 50 and Rs 30 at the end of years 1, 2 and 3. The nominal discount rate is 15% and inflation is 10%. What is the NPV? The cash flows are real but the rate is nominal, so convert one of them.
Worked example: method 1, nominal cash flows at the nominal rate
| Year | Nominal cash flow |
|---|---|
| 0 | −100 |
| 1 | 35 × 1.10 = 38.50 |
| 2 | 50 × 1.10² = 60.50 |
| 3 | 30 × 1.10³ = 39.93 |
Answer: about Rs 5.5.
Answer: about Rs 5.5 again. Consistent treatment of inflation gives the same NPV either way. (The exact real rate is 4.545%; rounding it to 4.5% shifts the NPV only slightly.)
4.13 Full Project Appraisal (Problem 6)
4.13.1 The Data
A project requires Rs 12,000 today in plant and machinery. The machinery can be dismantled and sold for net proceeds of Rs 1,949 at the end of year 7 (the forecast salvage value). For tax purposes the company must fully depreciate the investment to zero salvage value over a 6-year useful life using the straight-line method. On sale, tax is payable at 21% on the difference between the sale price and the net book value. All figures are nominal; the nominal opportunity cost of capital for projects of similar risk is 20%. The company can use any tax loss on the project to shield income from the rest of its business, and all cash flows occur at year-end. Is the investment worth undertaking?
Year-end forecasts (Rs):
| 0 | 1 | 2 | 3 | 4 | 5 | 6 | |
|---|---|---|---|---|---|---|---|
| Investment in working capital (NWC level) | 550 | 1,289 | 3,261 | 4,890 | 3,583 | 2,002 | |
| Sales | 523 | 12,887 | 32,610 | 48,901 | 35,834 | 19,717 | |
| Cost of goods sold | 837 | 7,729 | 19,552 | 29,345 | 21,492 | 11,830 | |
| Other costs (excluding depreciation) | 4,000 | 2,200 | 1,210 | 1,331 | 1,464 | 1,611 | 1,772 |
4.13.2 Step 1: Depreciation
Answer: Rs 2,000 a year in years 1 to 6.
4.13.3 Step 2: Project Income Statement
Profit before tax = Sales − COGS − Other costs − Depreciation. For year 1:
A negative tax does not mean the government pays the company. It means the project's loss reduces the company's total taxable income, so the company saves Rs 948 in taxes in year 1 (this is why the problem says the loss can shield income from the rest of the business).
| Income statement (Rs) | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
|---|---|---|---|---|---|---|---|
| Sales | 523 | 12,887 | 32,610 | 48,901 | 35,834 | 19,717 | |
| Cost of goods sold | 837 | 7,729 | 19,552 | 29,345 | 21,492 | 11,830 | |
| Other costs | 4,000 | 2,200 | 1,210 | 1,331 | 1,464 | 1,611 | 1,772 |
| Depreciation | 2,000 | 2,000 | 2,000 | 2,000 | 2,000 | 2,000 | |
| Profit before tax | −4,000 | −4,514 | 1,948 | 9,727 | 16,092 | 10,731 | 4,115 |
| Tax at 21% | −840 | −948 | 409 | 2,043 | 3,379 | 2,254 | 864 |
| Profit after tax | −3,160 | −3,566 | 1,539 | 7,684 | 12,713 | 8,477 | 3,251 |
4.13.4 Step 3: Operating Cash Flow (Bottom-Up)
| Rs | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|---|
| Profit after tax | −3,160 | −3,566 | 1,539 | 7,684 | 12,713 | 8,477 | 3,251 | |
| Depreciation | 2,000 | 2,000 | 2,000 | 2,000 | 2,000 | 2,000 | ||
| OCF | −3,160 | −1,566 | 3,539 | 9,684 | 14,713 | 10,477 | 5,251 |
The top-down or tax shield approach would give the same OCF.
4.13.5 Step 4: Capital Investment and After-Tax Salvage
The investment is an outflow of Rs 12,000 at year 0. The disposal happens at year 7, when the net book value is zero (the asset was fully depreciated by year 6).
Answer: Rs 1,540 inflow at year 7.
4.13.6 Step 5: Working Capital Cash Flows
The forecast row gives the level of working capital in years 1 to 6; it is fully recovered at year 7. The cash flow each year is minus the change in that level. For year 1:
| Rs | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| NWC level | 550 | 1,289 | 3,261 | 4,890 | 3,583 | 2,002 | 0 |
| Cash flow from changes in NWC | −550 | −739 | −1,972 | −1,629 | +1,307 | +1,581 | +2,002 |
4.13.7 Step 6: Net Cash Flow and NPV
NCF = OCF + cash flow from capital investment and disposal + cash flow from changes in working capital. For year 1: −1,566 + 0 − 550 = −2,116.
| Rs | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|---|
| (1) OCF | −3,160 | −1,566 | 3,539 | 9,684 | 14,713 | 10,477 | 5,251 | |
| (2) Capital investment and disposal | −12,000 | 1,540 | ||||||
| (3) Changes in working capital | −550 | −739 | −1,972 | −1,629 | 1,307 | 1,581 | 2,002 | |
| Net cash flow (1 + 2 + 3) | −15,160 | −2,116 | 2,800 | 7,712 | 13,084 | 11,784 | 6,832 | 3,542 |
Answer: NPV = +Rs 3,806. The project adds to shareholder wealth, so accept it.
Exam tip: The appraisal is a checklist. (1) Depreciation from the tax rules, (2) income statement down to PAT, letting negative tax stand as a tax saving, (3) OCF = PAT + depreciation, (4) capex at year 0 and salvage net of tax at disposal, (5) minus the change in NWC each year, with full recovery at the end, (6) add the three, discount at the nominal rate because the forecasts are nominal (Rule 3), and ignore any financing flows (Rule 4).